Work Profile Report [15W389]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 811/।।।(2)/14-50 (प्रा0आ0) /2013 दिनांक 08.02.2014
TS Amount (lakhs) : 725 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
725.00
Resanction Cost :
725.00
Tentative Cost :
483.00
Saving
242.00
Exp. Upto Last Fy :
436.32
For CFY 2025-2026
Remaining :
288.68
Demand :
25.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
436.32
Work completed
Sanction on : 11 years 2 months ago
08 Feb 2014
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 2 years 3 months ago
31 Dec 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का भुगतान शेष है। -- as on 10-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand