Work Profile Report [130W14]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : job no. RO/UK/AP2022-23-NH-58(newNH 07)/633
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
19254.11
Resanction Cost :
14259.25
Tentative Cost :
14259.25
Exp. Upto Last Fy :
5,181.47
For CFY 2025-2026
Remaining :
9,077.78
Demand :
4,755.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
5,181.47
Construction Started
Sanction on : 2 years 5 months ago
09 Jan 2023
Physical Progress:
At start of FY 2025-2026 :
79 %
Up to Date :
90 %
Tentative Completion date on : 1 month 2 days from now
12 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work in progress -- as on 01-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: