Work Profile Report [12W600]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E File No-49071/57 Date-29.08.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
795.69
Resanction Cost :
795.69
Tentative Cost :
795.69
Exp. Upto Last Fy :
404.96
For CFY 2025-2026
Remaining :
390.73
Demand :
390.73
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
404.96
Construction Started
Sanction on : 7 months 3 weeks ago
29 Aug 2024
Physical Progress:
At start of FY 2025-2026 :
47 %
Up to Date :
47 %
Tentative Completion date on : 2 months 4 days from now
29 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
डी0बी0एम0 का कार्य पूर्ण, सोल्डर में इण्टर लांकिंग टाइल्स हेतु जी03 एवं नाली का कार्य प्रगति पर। नहर कवरिंग हेतु RCC का कार्य प्रगति पर। -- as on 05-Feb-2025
Assets :
Work not linked with IM