Work Profile Report [12W547]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 256/।।। (3) / 2024 -01 (सी0आर0आई0एफ0) 2022 लोक निर्माण अनुभाग-3 देहरादून दिनांक 29.02.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1700.00
Resanction Cost :
1662.62
Tentative Cost :
1662.62
Exp. Upto Last Fy :
1,542.13
For CFY 2025-2026
Remaining :
120.49
Demand :
120.49
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1,542.13
Construction Started
Sanction on : 1 year 1 month ago
29 Feb 2024
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
80 %
Tentative Completion date on : 1 month 2 weeks from now
13 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 37.38 has been recorded as expected cost of work reduced from 1700 to 1662.62 . -- as on 19-Apr-2025
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: RCC Bridge on S.H. 10 Km. 18