Work Profile Report [12W543]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई-फाईल सं0 47302 लोक निर्माण अनुभाग-2 देहरादून दिनांक 27.02.2024
TS Amount (lakhs) : 53.89 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
53.89
Resanction Cost :
53.89
Tentative Cost :
53.89
Exp. Upto Last Fy :
50.95
For CFY 2025-2026
Remaining :
2.94
Demand :
2.94
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
50.95
Work completed
Sanction on : 1 year 1 month ago
27 Feb 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 6 months 3 weeks ago
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 27-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand