Work Profile Report [12W408]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 1187/।।। (2)/19-57 (एम0एल0ए0)/2017 दिनांक 27.02.2019
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
4.00
Resanction Cost :
4.00
Tentative Cost :
4.00
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
4.00
Demand :
0.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 6 years 1 month ago
27 Feb 2019
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 3 years 3 weeks ago
31 Mar 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Letter for directions is written to higher authority for construction of road in 5 m width vide letter no. 2040/8C Dt. 05.12.2024 -- as on 02-Jan-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: