Work Profile Report [12W379]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0दे0 सं0 1710/।।।(2)/18-57(एम0एल0ए0)/2017 दि0 02.05.2018
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
49.75
Resanction Cost :
49.75
Tentative Cost :
49.75
Exp. Upto Last Fy :
0.14
For CFY 2025-2026
Remaining :
49.61
Demand :
0.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.14
Construction Started
Sanction on : 6 years 11 months ago
02 May 2018
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
5 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रस्ताव गठित, राजस्व विभाग एवं वन विभाग के संबधितों के हस्ताक्षर कराये जा रहे है। -- as on 03-Jan-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand