Work Profile Report [129W722]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : लोक निर्माण अनुभाग-2, उत्तराखण्ड शासनादेश ई फाईल सं0-49430, दिनांक 29.11.2023
TS Amount (lakhs) : 45.37 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
45.37
Resanction Cost :
45.37
Tentative Cost :
45.37
Exp. Upto Last Fy :
37.58
For CFY 2025-2026
Remaining :
7.79
Demand :
7.79
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
37.58
Work completed
Sanction on : 1 year 4 months ago
29 Nov 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 months 2 weeks ago
06 Dec 2024
Actual Completion Date : 4 months 2 weeks ago
06 Dec 2024
Physical Linear Components
Remark
Work Complete. Date 06-12-2024 -- as on 09-Dec-2024
Assets :
Work not linked with IM