Work Profile Report [129W651]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई फाईल सं0-47899, लोक निर्माण अनुभाग-2 दिनांक 13.03.2023
TS Amount (lakhs) : 79.33 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
79.33
Resanction Cost :
79.33
Tentative Cost :
79.33
Exp. Upto Last Fy :
79.41
For CFY 2025-2026
Remaining :
-0.08
Demand :
0.78
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
79.41
In Maintenance After Completion
Sanction on : 2 years 1 month ago
13 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 1 month ago
15 Mar 2024
Actual Completion Date : 1 year 3 weeks ago
30 Mar 2024
Physical Linear Components
Remark
कार्य पूर्ण I -- as on 06-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand