Work Profile Report [11W669]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन के शासनादेश संख्या- ई फाईल संख्या 56165/61 लोक निर्माण अनुभाग-2 देहरादून दिनांक 10.03.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
149.22
Resanction Cost :
149.22
Tentative Cost :
149.22
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
149.12
Demand :
110.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
in Tendering Stage
Sanction on : 1 month 2 weeks ago
10 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 149.22 has been counted as tentative cost increased from to 149.22 . कार्य में निविदा आमंत्रित की जा चुकी है। -- as on 24-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand