Administrative Approval Detail : शासनादेश संख्या ई-फाईल संख्या 56165/61 लोक निर्माण अनुभाग-2 दिनांक 20.01.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
44.69
Resanction Cost :
44.69
Tentative Cost :
44.69
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
44.59
Demand :
30.00
Allotment :
17.14
Exp in CFY :
4.59
Total Up to Date Exp :
4.69
Construction Started
Sanction on : 7 months 2 weeks ago
20 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
22 %
Tentative Completion date on : 1 week 2 days ago
31 Aug 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0एस0बी0 एवं क्रॉस ड्रैनेज का कार्य पूर्ण। जी-2 का कार्य प्रगति पर। -- as on 02-Sep-2025
Assets :
Work not linked with IM