Work Profile Report [11W660]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश संख्या ई-फाईल संख्या 56165/61 लोक निर्माण अनुभाग-2 दिनांक 17.12.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
30.00
Resanction Cost :
30.00
Tentative Cost :
30.00
Exp. Upto Last Fy :
13.38
For CFY 2025-2026
Remaining :
16.62
Demand :
16.62
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
13.38
Construction Started
Sanction on : 4 months 1 week ago
17 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
95 %
Tentative Completion date on : 1 week 5 days ago
12 Apr 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 का कार्य पूर्ण। नाली का कार्य प्रगति पर। -- as on 09-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: