Work Profile Report [11W568]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन, लोक निर्माण अनुभाग-2 ई्र-फाईल पत्रावली 48808 दिनांक 15.03.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
9.00
Resanction Cost :
9.00
Tentative Cost :
9.00
Exp. Upto Last Fy :
0.12
For CFY 2025-2026
Remaining :
8.88
Demand :
8.88
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.12
Alignment Approved
Sanction on : 2 years 1 month ago
15 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
50 %
Up to Date :
50 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वन भूमि प्रस्ताव का गठन की कार्यवाही प्रगति पर है। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: