Work Profile Report [10W399]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E-File No. 54192/57 dt. 17-03-2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
69.73
Resanction Cost :
69.73
Tentative Cost :
69.73
Exp. Upto Last Fy :
0.20
For CFY 2025-2026
Remaining :
69.53
Demand :
60.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.20
none
Sanction on : 2 months 3 weeks ago
17 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
5 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 28-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand