Work Profile Report [8W295]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : GO No 5254(1)/III(2)/21-04(MLA)/2017 TC III
TS Amount (lakhs) : 192.04 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
192.04
Resanction Cost :
205.37
Tentative Cost :
194.75
Saving
10.62
Exp. Upto Last Fy :
192.08
For CFY 2025-2026
Remaining :
13.29
Demand :
0.89
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
192.08
In Maintenance After Completion
Sanction on : 4 years 1 month ago
30 Oct 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 6 months ago
20 May 2024
Actual Completion Date : 1 year 6 months ago
20 May 2024
Physical Linear Components
Remark
Overall Saving 10.62 has been recorded as expected cost of work reduced from 205.37 to 194.75 . -- as on 18-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: