Work Profile Report [8W21]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : 827/।।।-2/06-76 (प्रा॰आ॰)/05 दि॰ 28.03.06
TS Amount (lakhs) : 162.48 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
162.48
Resanction Cost :
162.48
Tentative Cost :
80.00
Saving
82.48
Exp. Upto Last Fy :
63.48
For CFY 2025-2026
Remaining :
99.00
Demand :
5.50
Allotment :
6.16
Exp in CFY :
6.16
Total Up to Date Exp :
69.65
Construction Started
Sanction on : 19 years 8 months ago
28 Mar 2006
Physical Progress:
At start of FY 2025-2026 :
70 %
Up to Date :
70 %
Tentative Completion date on : 3 months 2 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 82.48 has been recorded as expected cost of work reduced from 162.48 to 80 . -- as on 11-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: