Administrative Approval Detail : 827/।।।-2/06-76 (प्रा॰आ॰)/05 दि॰ 28.03.06

TS Amount (lakhs) : 162.48 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

162.48

Resanction Cost :

162.48

Tentative Cost :

80.00

Saving

82.48

Exp. Upto Last Fy :

63.48

For CFY 2025-2026

Remaining :

99.00

Demand :

5.50

Allotment :

6.16

Exp in CFY :

6.16

Total Up to Date Exp :

69.65

Construction Started

Sanction on : 19 years 8 months ago

28 Mar 2006

Physical Progress:

At start of FY 2025-2026 :

70 %

Up to Date :

70 %

Tentative Completion date on : 3 months 2 weeks from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
6
6
0.000
6
0.000
0.000

Remark

view all

Overall Saving 82.48 has been recorded as expected cost of work reduced from 162.48 to 80 . -- as on 11-Dec-2025

Rating : 70

Forest Case Pending At : 11: AIP Division

Hindrance / Bottleneck : To Cancel

Assets :

Work not linked with IM

Bridges on The Basis of AI: