Work Profile Report [71W1077]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली 247724/2024/45994 दिनांक 18/10/2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
236.31
Resanction Cost :
236.31
Tentative Cost :
236.31
Exp. Upto Last Fy :
0.17
For CFY 2025-2026
Remaining :
236.14
Demand :
236.14
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.17
Construction Started
Sanction on : 6 months 6 days ago
18 Oct 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 8 months 1 hour from now
25 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 11-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: