Work Profile Report [70W600]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 50713, दिनांक 06.12.2024
TS Amount (lakhs) : 258.98 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
258.98
Resanction Cost :
258.98
Tentative Cost :
258.98
Exp. Upto Last Fy :
11.21
For CFY 2025-2026
Remaining :
247.77
Demand :
232.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
11.21
Construction Started
Sanction on : 4 months 2 weeks ago
06 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
5 %
Tentative Completion date on : 6 months 3 weeks from now
18 Nov 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अनुबन्ध गठित। कार्य प्रगति पर। -- as on 25-Feb-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand