Work Profile Report [70W532]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 26505, दि0 16.03.2024
TS Amount (lakhs) : 231.48 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
231.48
Resanction Cost :
231.48
Tentative Cost :
231.48
Exp. Upto Last Fy :
214.23
For CFY 2025-2026
Remaining :
17.25
Demand :
10.32
Allotment :
10.00
Exp in CFY :
0.00
Total Up to Date Exp :
214.23
Construction Started
Sanction on : 1 year 2 months ago
16 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
95 %
Tentative Completion date on : 3 weeks 4 days ago
15 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 01-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: