Work Profile Report [70W35]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 1648(1)/111(2)/13-52(प्र्रा0आ0)/2012 दिनांक 04.03.2013
TS Amount (lakhs) : 7.56 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
18.90
Resanction Cost :
18.90
Tentative Cost :
18.90
Exp. Upto Last Fy :
17.15
For CFY 2025-2026
Remaining :
1.75
Demand :
1.75
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
17.15
Construction Started
Sanction on : 12 years 1 month ago
04 Mar 2013
Physical Progress:
At start of FY 2025-2026 :
90 %
Up to Date :
90 %
Tentative Completion date on : 3 months 6 days from now
31 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
द्वितीय चरण की स्वीकृति प्राप्त। मुआवजा 90 प्रतिशत वितरित। -- as on 29-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand