Work Profile Report [70W325]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 6034/111(2) /21-40 (एम0एल0ए0)/2017 टी0सी0 दिनांक 14.12.2021
TS Amount (lakhs) : 46.69 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
46.69
Resanction Cost :
46.69
Tentative Cost :
46.69
Exp. Upto Last Fy :
40.75
For CFY 2025-2026
Remaining :
5.94
Demand :
5.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
40.75
Work completed
Sanction on : 3 years 4 months ago
14 Dec 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 5 days 1 hour from now
30 Apr 2025
Actual Completion Date : 2 years 3 months ago
31 Dec 2022
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 08-Nov-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: