Work Profile Report [70W318]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 428(1)/111(2)/22-40(एम0एल0ए0)2017 दिनांक 06.01.2022
TS Amount (lakhs) : 85.46 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
85.46
Resanction Cost :
85.46
Tentative Cost :
85.46
Exp. Upto Last Fy :
0.69
For CFY 2025-2026
Remaining :
84.77
Demand :
84.77
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.69
Construction Started
Sanction on : 3 years 3 months ago
06 Jan 2022
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
5 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
ग्रामीणों के साथ विवाद सुलझा दिया गया है। निर्माण कार्य प्रारम्भ किया जा रहा है। -- as on 09-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand