Work Profile Report [70W296]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 5660(1)/।।।(2)/21-40(एम0एल0ए0)/2017 टी0सी0 -01 दिनांक 17.11.2021
TS Amount (lakhs) : 37.94 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
37.94
Resanction Cost :
37.94
Tentative Cost :
37.94
Exp. Upto Last Fy :
24.35
For CFY 2025-2026
Remaining :
13.59
Demand :
13.59
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
24.35
Construction Started
Sanction on : 3 years 5 months ago
17 Nov 2021
Physical Progress:
At start of FY 2025-2026 :
60 %
Up to Date :
60 %
Tentative Completion date on : 11 months 6 days from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.800 किमी0 में पहाड़ कटान का कार्य पूर्ण। शेष में ग्रामीणों द्वारा विवाद किया जा रहा है। -- as on 09-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: