Work Profile Report [70W282]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 3324/।।।(2)/21 -11 (मु0मं0घो0)/2015 दिनांक 03.09.2021
TS Amount (lakhs) : 142.06 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
142.06
Resanction Cost :
142.06
Tentative Cost :
142.06
Exp. Upto Last Fy :
127.66
For CFY 2025-2026
Remaining :
14.40
Demand :
14.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
127.66
Work completed
Sanction on : 3 years 7 months ago
03 Sep 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 month 6 days from now
31 May 2025
Actual Completion Date : 10 months 2 weeks ago
06 Jun 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 29-Mar-2025