Work Profile Report [6W827]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी बागे0 के पत्र सं0 716/जि0यो0(1)/2023-24 दिनांक 06.07.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
40.00
Resanction Cost :
40.00
Tentative Cost :
40.00
Exp. Upto Last Fy :
1.39
For CFY 2025-2026
Remaining :
38.61
Demand :
36.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1.39
Construction Started
Sanction on : 1 year 9 months ago
06 Jul 2023
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
10 %
Tentative Completion date on : 6 months 6 days from now
31 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 04-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand