Work Profile Report [6W571]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 1179/।।।(2)/19-46(एम0एल0ए0)/2017 टी0सी0-।ं दिनांक 27 फरवरी 2019
TS Amount (lakhs) : 177.07 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
177.07
Resanction Cost :
177.07
Tentative Cost :
176.54
Saving
0.53
Exp. Upto Last Fy :
176.54
For CFY 2025-2026
Remaining :
0.53
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
176.54
In Maintenance After Completion
Sanction on : 6 years 2 months ago
27 Feb 2019
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 years 4 months ago
27 Dec 2020
Actual Completion Date : 5 years 1 month ago
01 Apr 2020
Physical Linear Components
Remark
Overall Saving 0.53 has been recorded as expected cost of work reduced from 177.07 to 176.54 . -- as on 02-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand