Work Profile Report [69W388]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई-पत्रावली सं0 36086 लोक निर्माण अनुभाग-2 देहरादून दि0 27.01.2025
TS Amount (lakhs) : 158.62 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
158.62
Resanction Cost :
158.62
Tentative Cost :
158.62
Exp. Upto Last Fy :
0.09
For CFY 2025-2026
Remaining :
158.53
Demand :
130.00
Allotment :
35.07
Exp in CFY :
35.07
Total Up to Date Exp :
35.16
Construction Started
Sanction on : 4 months 1 week ago
27 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 9 months 3 weeks from now
04 Apr 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 28-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: