Work Profile Report [69W160]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 4416/111 (2)/15-04 (मु0म0घो0)/2015 दि0 27.05.2015
TS Amount (lakhs) : 101.98 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
195.62
Resanction Cost :
195.62
Tentative Cost :
195.62
Exp. Upto Last Fy :
168.86
For CFY 2025-2026
Remaining :
26.76
Demand :
26.76
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
168.86
Construction Started
Sanction on : 9 years 10 months ago
27 May 2015
Physical Progress:
At start of FY 2025-2026 :
70 %
Up to Date :
70 %
Tentative Completion date on : 2 months 3 weeks ago
31 Jan 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति में है। -- as on 13-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: