Administrative Approval Detail : उत्तराखण्ड शासन की ई0-पत्रावली सं0-66794 लोक निर्माण अनुभाग-2 दिनांक 14 मार्च 2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
168.37
Resanction Cost :
168.37
Tentative Cost :
168.37
Exp. Upto Last Fy :
111.95
For CFY 2025-2026
Remaining :
56.42
Demand :
49.96
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
111.95
Construction Started
Sanction on : 1 year 1 month ago
14 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
75 %
Tentative Completion date on : 1 month 2 weeks from now
15 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
टाॅप कोट का कार्य पूर्ण, पी0सी0 का कार्य प्रगति पर है -- as on 07-Apr-2025