Work Profile Report [68W106]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 1542/111(2)/09-22(मु0म0 धोषणा)/09 दि0 31.03.2010
TS Amount (lakhs) : 895.79 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
945.00
Resanction Cost :
945.00
Tentative Cost :
945.00
Exp. Upto Last Fy :
896.84
For CFY 2025-2026
Remaining :
48.16
Demand :
40.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
896.84
Work completed
Sanction on : 15 years 3 weeks ago
31 Mar 2010
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 3 weeks ago
28 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अवशेष कास्तकारों को मुआवजा भुगतान की कार्यवाही की जा रही है। -- as on 23-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: