Work Profile Report [67W788]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली सं0 37890 दि0 19.07.2027
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
161.60
Resanction Cost :
161.60
Tentative Cost :
161.60
Exp. Upto Last Fy :
57.49
For CFY 2025-2026
Remaining :
104.11
Demand :
98.00
Allotment :
98.00
Exp in CFY :
75.59
Total Up to Date Exp :
133.08
Construction Started
Sanction on : 10 months 3 weeks ago
19 Jul 2024
Physical Progress:
At start of FY 2025-2026 :
50 %
Up to Date :
90 %
Tentative Completion date on : 2 months 2 weeks from now
28 Aug 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 05-Jun-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: