Work Profile Report [67W761]
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली सं0 60081 दि0 14.03.2024
TS Amount (lakhs) : 569.02 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
226.02
Resanction Cost :
226.02
Tentative Cost :
226.02
Exp. Upto Last Fy :
169.44
For CFY 2025-2026
Remaining :
56.58
Demand :
56.00
Allotment :
30.00
Exp in CFY :
8.94
Total Up to Date Exp :
178.38
Work completed
Sanction on : 1 year 2 months ago
14 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 9 months 3 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्य शेष। -- as on 19-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: