Work Profile Report [67W743]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली संख्या-48456 दि0 10.08.2023
TS Amount (lakhs) : 160.48 Lacs
Budget Financial Head : अनुरक्षण ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
160.48
Resanction Cost :
160.48
Tentative Cost :
160.48
Exp. Upto Last Fy :
127.53
For CFY 2025-2026
Remaining :
32.95
Demand :
32.95
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
127.53
Work completed
Sanction on : 1 year 8 months ago
10 Aug 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 9 months 4 weeks ago
25 Jun 2024
Actual Completion Date : 9 months 4 weeks ago
25 Jun 2024
Physical Linear Components
Remark
कार्य पूर्ण। दायित्य शेष। -- as on 03-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: