Work Profile Report [67W212]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 4110/111घ्2घ्/11-55घ्प्रा0आ0घ्/2011 दि0 16-09-2011
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
88.20
Resanction Cost :
88.20
Tentative Cost :
88.20
Exp. Upto Last Fy :
29.21
For CFY 2025-2026
Remaining :
58.99
Demand :
40.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
29.21
Phase1 DPR Submitted
Sanction on : 13 years 7 months ago
16 Sep 2011
Physical Progress:
At start of FY 2025-2026 :
30 %
Up to Date :
30 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
द्वितीय चरण का कार्य पूर्ण। अवशेष प्रतिकर भुगतान की कार्यवाही गतिमान है। -- as on 23-Apr-2025