Work Profile Report [5W943]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-।/136376/2023, ई फाईल संख्या-57670, दिनांक 10.07.2023
TS Amount (lakhs) : 118.5 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
118.50
Resanction Cost :
118.50
Tentative Cost :
118.50
Exp. Upto Last Fy :
88.25
For CFY 2025-2026
Remaining :
30.25
Demand :
17.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
88.25
Construction Started
Sanction on : 1 year 9 months ago
10 Jul 2023
Physical Progress:
At start of FY 2025-2026 :
90 %
Up to Date :
90 %
Tentative Completion date on : 6 months 2 weeks ago
08 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान कार्य पूर्ण। -- as on 27-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand