Work Profile Report [5W612]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 671/।।।(2)/16-46(एम.एल.ए.)/2015 टी0सी0, दिनांक 22.03.2016
TS Amount (lakhs) : 121.34 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
121.34
Resanction Cost :
121.34
Tentative Cost :
91.34
Saving
30.00
Exp. Upto Last Fy :
48.50
For CFY 2025-2026
Remaining :
72.84
Demand :
20.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
48.50
Work completed
Sanction on : 9 years 1 month ago
22 Mar 2016
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
95 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
आवश्यक स्थानों पर स्कपर निर्माण किया जाना है। -- as on 12-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: