Work Profile Report [59W2307]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-50282/28 दि0 17.12.2024
TS Amount (lakhs) : 70.78 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
70.78
Resanction Cost :
70.78
Tentative Cost :
70.78
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
70.78
Demand :
70.50
Allotment :
57.42
Exp in CFY :
57.42
Total Up to Date Exp :
57.42
Work completed
Sanction on : 5 months 3 weeks ago
17 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
50 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्यपूर्ण 04/2025 -- as on 30-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: