Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-55435/30 दि0 02.12.2024
TS Amount (lakhs) : 55.85 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
55.85
Resanction Cost :
55.85
Tentative Cost :
55.85
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
55.85
Demand :
55.50
Allotment :
2.86
Exp in CFY :
2.86
Total Up to Date Exp :
2.86
Construction Started
Sanction on : 6 months 1 week ago
02 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
73 %
Tentative Completion date on : 1 month 4 days from now
14 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
800 मी0 लम्बाई में कार्यपूर्ण, शेष कार्य प्रगति में। -- as on 31-May-2025