Work Profile Report [59W2302]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-49430/34 दि0 11.11.2024
TS Amount (lakhs) : 47.48 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
47.48
Resanction Cost :
47.48
Tentative Cost :
47.48
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
47.48
Demand :
47.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 5 months 1 week ago
11 Nov 2024
Physical Progress:
At start of FY 2025-2026 :
77 %
Up to Date :
77 %
Tentative Completion date on : 1 month 4 weeks from now
24 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
600 मी0 लम्बाई में इण्टरलोकिंग टाईल्स का कार्य पूर्ण, शेष कार्य प्रगति में। -- as on 25-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: