Work Profile Report [59W2283]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-66213/28 दि0 07.10.2024
TS Amount (lakhs) : 123.94 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
123.94
Resanction Cost :
123.94
Tentative Cost :
123.94
Exp. Upto Last Fy :
40.35
For CFY 2025-2026
Remaining :
83.59
Demand :
83.50
Allotment :
68.46
Exp in CFY :
68.46
Total Up to Date Exp :
108.82
Work completed
Sanction on : 8 months 2 days ago
07 Oct 2024
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
100 %
Tentative Completion date on : 2 weeks 6 days from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्यपूर्ण 04/2025 -- as on 30-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand