Work Profile Report [59W2199]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-57969 दिनांक 05.10.2023
TS Amount (lakhs) : 29.69 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
29.69
Resanction Cost :
29.69
Tentative Cost :
29.69
Exp. Upto Last Fy :
25.06
For CFY 2025-2026
Remaining :
4.63
Demand :
4.50
Allotment :
3.86
Exp in CFY :
3.86
Total Up to Date Exp :
28.92
Work completed
Sanction on : 1 year 8 months ago
05 Oct 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 10 months 3 weeks ago
19 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्यपूर्ण दायित्वों का भुगतान शेष। -- as on 02-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: