Work Profile Report [59W2130]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-55435 दिनांक 31.07.2023
TS Amount (lakhs) : 60.64 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
60.64
Resanction Cost :
60.64
Tentative Cost :
60.64
Exp. Upto Last Fy :
23.06
For CFY 2025-2026
Remaining :
37.58
Demand :
37.50
Allotment :
24.50
Exp in CFY :
4.94
Total Up to Date Exp :
28.00
Construction Started
Sanction on : 1 year 10 months ago
31 Jul 2023
Physical Progress:
At start of FY 2025-2026 :
45 %
Up to Date :
90 %
Tentative Completion date on : 2 months 1 week ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
1.700 किमी0 लम्बाई में कार्यपूर्ण, शेष कार्य प्रगति पर है । -- as on 31-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand