Administrative Approval Detail : 1/270756/2025/PWD2-BUD/ANBU/28/2023-III-2-Public Works Department(1) Dt. 27-01-2025
TS Amount (lakhs) : 53.36 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
53.36
Resanction Cost :
53.36
Tentative Cost :
53.36
Exp. Upto Last Fy :
0.13
For CFY 2025-2026
Remaining :
53.23
Demand :
40.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.13
Construction Started
Sanction on : 4 months 1 week ago
27 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
60 %
Tentative Completion date on : 9 months 3 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.40 कि0मी0 में कार्यपूर्ण, शेष कार्य प्रगति में है। -- as on 29-May-2025