Administrative Approval Detail : 1/262647/2024/PWD2-BUD/ANBU/21/2023-III-2-Public Works Department
TS Amount (lakhs) : 57.47 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
57.47
Resanction Cost :
57.47
Tentative Cost :
57.47
Exp. Upto Last Fy :
10.46
For CFY 2025-2026
Remaining :
47.01
Demand :
45.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
10.46
Construction Started
Sanction on : 4 months 5 days ago
19 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
40 %
Up to Date :
50 %
Tentative Completion date on : 4 months 6 days from now
31 Aug 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.50 कि0मी0 में टाॅप कोट तक कार्य पूर्ण, 0.30 कि0मी0 में टाईल्स कार्य पूर्ण शेष कार्य प्रगति में है। -- as on 27-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: