Work Profile Report [55W1980]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/261888/2024/PWD2-BUD/ANBU/28/2023-III-2-Public Works Department-Part(1)
TS Amount (lakhs) : 60.44 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
60.44
Resanction Cost :
60.44
Tentative Cost :
60.44
Exp. Upto Last Fy :
0.08
For CFY 2025-2026
Remaining :
60.36
Demand :
50.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.08
Construction Started
Sanction on : 4 months 1 week ago
17 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
25 %
Up to Date :
25 %
Tentative Completion date on : 2 months 5 days from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.15 कि0मी0 में टाईल्स कार्य पूर्ण शेष कार्य प्रगति में है। -- as on 27-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand