Work Profile Report [55W1949]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/241293/2024/PWD2-BUD/ANBU/32/2023-III-2-Public Works Department
TS Amount (lakhs) : 51.16 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
51.16
Resanction Cost :
51.16
Tentative Cost :
51.16
Exp. Upto Last Fy :
16.65
For CFY 2025-2026
Remaining :
34.51
Demand :
30.00
Allotment :
14.90
Exp in CFY :
14.90
Total Up to Date Exp :
31.55
Construction Started
Sanction on : 8 months 3 weeks ago
19 Sep 2024
Physical Progress:
At start of FY 2025-2026 :
50 %
Up to Date :
95 %
Tentative Completion date on : 5 days 10 hours from now
15 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मार्ग कार्य पूर्ण, पटरी आदि कार्य प्रगति में है। -- as on 29-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: