Administrative Approval Detail : 1/239986/2024/PWD2-BUD/ANBU/32/2023-III-2-Public Works Department
TS Amount (lakhs) : 65.27 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
65.27
Resanction Cost :
65.27
Tentative Cost :
65.27
Exp. Upto Last Fy :
16.38
For CFY 2025-2026
Remaining :
48.89
Demand :
40.00
Allotment :
0.35
Exp in CFY :
0.35
Total Up to Date Exp :
16.73
Construction Started
Sanction on : 8 months 3 weeks ago
13 Sep 2024
Physical Progress:
At start of FY 2025-2026 :
40 %
Up to Date :
95 %
Tentative Completion date on : 2 weeks 6 days from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मार्ग कार्य पूर्ण, पटरी आदि कार्य प्रगति में है। -- as on 29-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: