Work Profile Report [55W1893]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. No. 1/174460/2023/PWD2-BUD/ANBU/28/2023-III-2-Public Works Department
TS Amount (lakhs) : 33.91 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
33.91
Resanction Cost :
33.91
Tentative Cost :
33.91
Exp. Upto Last Fy :
19.54
For CFY 2025-2026
Remaining :
14.37
Demand :
10.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
19.54
Construction Started
Sanction on : 1 year 5 months ago
12 Dec 2023
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
75 %
Tentative Completion date on : 9 months 3 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.60 कि0मी0 में कार्य पूर्ण, शेष लम्बाई में कार्य प्रगति में है। -- as on 29-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: