Work Profile Report [55W1253]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : श्शासनादेश संख्या 198/।।।(2)/17-35(एम0एल0ए0)/2017 लोक निर्माण अनुभाग-2 दिनांक 06.07.2017
TS Amount (lakhs) : 573.85 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
573.85
Resanction Cost :
573.85
Tentative Cost :
573.85
Exp. Upto Last Fy :
569.80
For CFY 2025-2026
Remaining :
4.05
Demand :
4.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
569.80
In Maintenance After Completion
Sanction on : 7 years 9 months ago
06 Jul 2017
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 5 years 3 days ago
21 Apr 2020
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्यपूर्ण । अनुरक्षण का कार्य कराया जायेगा, जिस हेतु धनावंटन की मांग की गयी है। -- as on 15-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand