Work Profile Report [53W1766]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 54048 दिनांक 20.03.2025
TS Amount (lakhs) : 196.42 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
196.42
Resanction Cost :
196.42
Tentative Cost :
196.42
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
196.32
Demand :
190.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
in Tendering Stage
Sanction on : 1 month 4 days ago
20 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 1 year 11 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
निविदा आमत्रिंत की गई है। -- as on 08-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand